AGLO 1974 NO. 34 >
Where a subcontractor's claim to a materialmen's lien is dependent upon his ability to show that the general contractor who employed him was acting as the agent for the owner of the property against which the lien is claimed, the subcontractor must be able to establish that the general contractor was registered under chapter 18.27 RCW, if applicable.